Orient House – a purpose-built 41-bed student building on Kettering Road – will provide accommodation for Northampton University, where there is a chronic shortage.
Works will include the refurbishment of an existing building to provide six one-bedroom apartments, alongside the construction of an 11,500 sq. ft. new build comprising three floors of six cluster flats with a total of 35 individual en-suite bedrooms.
The development will reinvigorate a previously derelict town centre building while addressing a need for purpose-built accommodation as identified by the university.
The scheme commenced for client, Abington Park Investments, in December 2022 and works are due to be completed in September 2023, in time for the new university year start.
The installation of the steel frame structure and roof structure finished at the end of May and brickwork, roof coverings and windows will now allow the interior fit out with dry-lining and mechanical and electrical works to move forward this summer.
To incorporate an additional seven bedrooms, alterations were made to the initial foundation design to include over 60 piles with a steel reinforced ground beam. To overcome the challenges of the small island site, careful planning and unconventional reordering of works was necessary to operate in the location, which was limited on space for site access, material deliveries, storage and plant and crane usage.
Lee Stow-Smith, project manager of Orient House at Fortis Vision, said: “We are pleased to be progressing with works for Orient House in Northampton, providing prime student residential accommodation for the university’s new September intake.